New Multi-Disciplinary Engineering/Neuro AI Building

Project Scope:

Construct a new, 75,000 square foot multidisciplinary engineering building that contains teaching labs as well as collaborative student spaces. This project kicked off in July of 2022, and the dates below will continue to be updated as we move through the various phases of work. Please check back soon for renderings and more detailed project updates. 

Status: 
Programming:
     Start date - August 2022
     End date - November 2022

Design:
 
     Start date - July 2023
     Estimated end date - December 2024

Construction:
     Estimated start date - January 2025
     Estimated end date - April 2027

Project/Construction Manager:
Eric Tiedermann
Stony Brook University Construction Manager
eric.tiedermann@stonybrook.edu

Budget:
Total approximate project cost: $125M